Skip to content Skip to Navigation

Back

Substantial Completion vs. Performance - What’s the Difference?

©2020, Ontario Association of Architects (OAA). Management of the Project articles may be reproduced and distributed, with appropriate credit included, for non-commercial use only. Commercial use requires prior written permission from the OAA. The OAA reserves all other rights.


 

 

A lot of people live with a lot of ambiguity in various forms of communication. Statistically, GenX and GenY are much more comfortable with ambiguity than older groups. While ambiguity may be accepted in casual communication, when administering a contract, it is important to be clear and unambiguous.

It recently cost one firm hours of effort involving the general contractor, the building inspector, the project designer, the design manager and the project architect to resolve an issue with a form letter because one of the parties didn’t recognize the difference between substantial completion and substantial performance.

 

Substantial Completion

This term originates in the Ontario Building Code as excerpted below:

 

1.3.3.4. Occupancy Permit — Certain Buildings of Residential Occupancy

(4) The chief building official or a person designated by the chief building official shall issue a permit authorizing occupation of a building described in Sentence (3), where,

(a) the structure of the building with respect to the dwelling unit to be occupied is substantially complete and ready to be used for its intended purpose,

 

With common usage, the term has come to be used more broadly as a catch-all for compliance with all the various applicable parameters stated in the building code under Division C, Subsection 1.3.3. It is most commonly encountered where an owner or tenant desires partial occupancy of a building.

For example, the term Substantial Completion is often applied to compliance with:

1.3.3. Occupancy of Buildings

1.3.3.1. Occupancy Permit — General

(1) Except as permitted in Sentence 1.3.3.2.(1), a person may occupy or permit to be occupied any building or part of it that has not been fully completed at the date of occupation where the chief building official or a person designated by the chief building official has issued a permit authorizing occupation of the building or part of it prior to its completion in accordance with Sentence (3).

(2) Sentence (1) does not apply in respect of the occupancy of a building to which Article 1.3.3.4. or 1.3.3.5. applies.

(3) The chief building official or a person designated by the chief building official shall issue a permit authorizing occupation of a building, where,

(a) the structure of the building or part of it is completed to the roof,

(b) the enclosing walls of the building or part of them are completed to the roof,

(c) the walls enclosing the space to be occupied are completed, including balcony guards,

(d) all required fire separations and closures are completed on all storeys to be occupied,

(e) all required exits are completed, including all fire separations, doors, door hardware, self-closing devices, guards and handrails, from the uppermost floor to be occupied down to grade level and below if an exit connects with lower storeys,

(f) all shafts including closures are completed to the floor-ceiling assembly above the storey to be occupied and have a temporary fire separation at such assembly,

(g) measures have been taken to prevent access to parts of the building and site that are incomplete or still under construction,

(h) floors, halls, lobbies and required means of egress are free of loose materials and other hazards,

(i) if service rooms should be in operation, required fire separations and closures are completed,

(j) all building drains, building sewers, water systems, drainage systems and venting systems are complete and tested as operational for the storeys to be occupied,

(k) required lighting, heating and electrical supply are provided for the suites, rooms and common areas to be occupied,

(l) required lighting in corridors, stairways and exits is completed and operational up to and including all storeys to be occupied,

(m) required standpipe, sprinkler and fire alarm systems are complete and operational up to and including all storeys to be occupied, together with required pumper connections for such standpipes and sprinklers,

(n) required fire extinguishers have been installed on all storeys to be occupied,

(o) main garbage rooms, chutes and ancillary services are completed to all storeys to be occupied,

(p) required firefighting access routes have been provided and are accessible, and

(q) the sewage system has been completed and is operational.

The term relates to a state of completion of a project primarily relating to health and life safety provisions and systems. There is no consideration of the dollar value of the work complete.

 

Substantial Performance

This term originates in the Construction Lien Act R.S.O. 1990, Chapter C.30, continues in the Construction Act, and is incorporated in the CCDC standard contracts. Substantial Performance is determined on the basis of suitability for the purpose intended and on a sliding percentage for 3 of 4 the value of work complete. With respect to substantial performance, the Construction Act differs only in changes to the threshold dollar amounts.

The Construction Lien Act states in part:

2. (1) For the purposes of this Act, a contract is substantially performed,

(a) when the improvement to be made under that contract or a substantial part thereof is ready for use or is being used for the purpose intended; and

(b) when the improvement to be made under that contract is capable of completion or, where there is a known defect, correction, at a cost not more than,

(i) 3 per cent of first $500,000 of the contract price,

(ii) 2 per cent of next $500,000 of the contract price, and

(iii) 1 per cent of the balance of the contract price. R.S.O. 1990, c. C.30, s. 2(2).

The Construction Act states in part:

2. (1) For the purposes of this Act, a contract is substantially performed,

(a) when the improvement to be made under that contract or a substantial part thereof is ready for use or is being used for the purpose intended; and

(b) when the improvement to be made under that contract is capable of completion or, where there is a known defect, correction, at a cost not more than,

(i) 3 per cent of first $1,000,000 of the contract price,

(ii) 2 per cent of next $1,000,000 of the contract price, and

(iii) 1 per cent of the balance of the contract price. R.S.O. 1990, c. C.30, s. 2(1).

The term relates to both a state of completion of a project and the dollar value of the work complete. Although they must be accounted for, there is no special concern or emphasis on health or life safety aspects of the project.

 

The Differences

Substantial Completion

Building Code only

Health & Life Safety focus

No financial threshold

Required for partial occupancy

Publication not required

Involves Chief Building Official


Substantial Performance

Construction Lien Act or Construction Act

Project as a whole

Sliding financial threshold

Based in part on suitability for occupancy

Publication required CBO not involved

  

From the preceding, it can be concluded that it is possible to be substantially complete without being substantially performed. Indeed, this is a common occurrence, and is desired when the owner or tenant wants to occupy a portion of a partially completed building.

This situation and a lack of understanding of the differences is responsible for the recommended disclaimer in a letter for partial occupancy, that it should not be considered by a lender as a 4 of 4 declaration of Substantial Performance.

It is a much rarer circumstance that a project could be considered Substantially Performed without being Substantially Complete.

There are times when ambiguity serves useful purposes; however, in this case, the clear and consistent usage and application of the terms Substantial Completion and Substantial Performance are important to profitable contract administration.

For additional information, refer to the OAA Practice Tip PT.10 series

 


These articles do not represent OAA policy or guidance but rather are based on the opinions and experiences of members of the OAA and are prepared for the benefit of the profession at large.


 
 
Share
Events banner

Events Calendar

Check out our events calendar for a wide array of online and in-person events. Also submit an event using our new online form.

MORE
Contracts banner

OAA Contract Suite

Did you know the OAA offers free contracts for its members and the general public? These downloadable standardized contracts make it easier for all to enter into fair, balanced business relationships.

MORE
BLOAAG banner

BLOAAG

Check out the OAA BLOAAg, an inclusive space for member engagement and OAA features.

MORE