Legislative Transition Period Notice:
The first day to submit for permit under Ontario’s new 2024 Building Code (OBC) is January 1, 2025 whereas the last day to submit for permit under the 2012 OBC is March 31, 2025.
Normally there is only one current version of a Practice Tip at any given time; however, during this transition period, there is both a 2012 OBC and a 2024 OBC version which are current. Members should confirm with the applicable municipality what their processes are before submitting for permit on behalf of their clients.
Refer to:
EABO Transition Infographic on 2024 Ontario Building Code.
2024 Ontario Building Code
PT.08 Participation In The Permit Process
Attachments
Attachment 1 - OAA Authorization as an Agent form
Attachment 2 - Distribution of Plans Examiner's Notices
References
Ontario Building Code
Building Code Act
OAA Regulatory Notices and Practice Tips such as Practice Tip PT.03
EABO forms such as Required Occupancy Documents Checklist
2012 Ontario Building Code
PT.08_ArchitectsParticipationInThePermitProcess
References
Schedule 1: Designer Information
Complete Application Best Practice Guide and FAQs
EABO Endorsed Review Commitment Form
EABO Final General Review Report Form
Attachments
Attachment A - OAA Authorization as an Agent form
Attachment B - Distribution of Plans Examiner's Notices
Updated: 2025/Mar/12